VIRGINIA DCR STORMWATER EXTENDED DETENTION (ED) PONDVERSION 1.6
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
SECTION 1: DESCRIPTION An Extended Detention (ED) Pond relies on 12 to 24 hour detention of stormwater runoff after each rain event. An under-sized outlet structure restricts stormwater flow so it backs up and is stored within a pond or wetland. The temporary ponding enables particulate pollutants to settle out and reduces the maximum peak discharge to the downstream channel thereby reducing the effective shear stress on downstream banks. ED differs from stormwater detention since it is designed to achieve a minimum drawdown time, rather than a maximum peak rate of flow (which is commonly used to design for peak discharge or flood control purposes and often detains flows for just a few minutes or hours). ED ponds rely on gravitational settling as their primary pollutant removal mechanism. Consequently, they generally provide fair to good removal for particulate pollutants but low or negligible removal for soluble pollutants, such as nitrate and soluble phosphorus. The use of ED alone generally has the lowest overall pollutant removal rate of any stormwater treatment option. As a result, ED is normally combined with wet ponds or constructed wetlands to maximize pollutant removal rates (see Table 1). Designers should note that ED ponds are the final element in the roof to stream runoff reduction sequence, and should only be considered if there is water quality or channel protection volume to manage after all other upland runoff reduction practices have been considered and properly credited. Designers may need to submit documentation to the local plan review authority showing that all runoff reduction efforts were explored and were found to be insufficient.
SECTION 2: LEVEL 1 AND 2 DESIGN TABLE The major design goal for the Chesapeake Bay is to maximize nutrient removal and runoff reduction. To this end, designers may choose to go with the baseline design (Level 1) or choose an enhanced Level 2 design that maximizes nutrient and runoff reduction. To qualify for the higher nutrient reduction rates for Level 2 design, ED ponds must be designed with a treatment volume equal to 1.25(Rv)(A). Table 2 lists the design criteria for Level 1 and 2 designs. See Section 5 for more detailed design guidelines.
SECTION 3: TYPICAL DETAILS
Figure 1. Typical Extended Detention Pond Details SECTION 4: PHYSICAL FEASIBILITY AND DESIGN APPLICATIONS The following feasibility issues need to be evaluated when ED ponds are considered as the final practice in a treatment train:
ED is normally combined with other stormwater treatment options such as wet ponds, sand filters and constructed wetlands to enhance its performance and appearance. The most common design variations for ED include:
Figure 1 illustrates several ED pond design variations. While ED ponds can provide for channel and flood protection, they will rarely provide adequate runoff reduction and pollutant removal to serve as a stand-alone compliance strategy. Therefore, designers should always maximize the use of upland runoff reduction practices, such as rooftop disconnections, small scale infiltration, rain tanks, bioretention, grass channels and dry swales that reduce runoff at its source (rather than treating the runoff at the terminus of the storm drain system). Upland runoff reduction practices can be used to satisfy most or all of the runoff reduction requirements at most sites, but an ED pond may still be needed to provide any remaining channel protection requirements. Upland runoff reduction practices will greatly reduce the size, footprint and cost of the downstream ED pond. SECTION 5: DESIGN CRITERIA 5.1. Overall Sizing Designers can use a site-adjusted Rv or CN to reflect the use of upland runoff reduction practices to compute the remaining volume that must be treated by the ED pond using the accepted local or state runoff reduction method. ED ponds are then designed to capture and treat the remaining runoff volume for the water quality storm and the channel protection storm (if needed). Runoff treatment credit may be taken for the entire water volume below the normal pool (including micropools, forebays and shallow marsh areas), as well as any temporary extended detention above the normal pool. To be eligible for the higher Level 2 design removal rates for water quality, the ED pond must be sized with 1.25 of the remaining water quality (but not any additional Channel Protection volume). 5.2. The Shortcut Method The kerplunk approach can be used to estimate the required volume for channel protection, using the NRCS methods presented in Appendix A of this Specification. 5.3. Required Geotechnical Testing Soil borings should be taken below the proposed embankment, in the vicinity of the proposed outlet area, and in at least two locations within the ED pond treatment area. Soil boring data is needed to (1) ascertain the physical characteristics of excavated material, (2) determine its adequacy for use as structural fill or spoil, (3) provide data for structural designs for outlet works (e.g., bearing capacity and buoyancy), (4) determine compaction/composition needs for the embankment, (5) fix the depth to groundwater and bedrock and (6) evaluate potential infiltration losses (and the consequent need for a liner). 5.4. Pretreatment Forebay Sediment forebays are considered an integral design feature to maintain the longevity of ED ponds. A forebay must be located at all major inlets to trap sediment and preserve the capacity of the main treatment cell.
5.5. Conveyance and Overflow
5.6. Internal Design Features
5.7. Landscaping and Planting Plan
For more guidance on planting trees and shrubs in ED pond buffers, consult Cappiella et al (2006) and Appendix E of the Introduction to the New Virginia Stormwater Design Specifications , as posted on the Virginia Stormwater BMP Clearinghouse web site). 5.8. Maintenance Reduction Features Several ED pond potential maintenance problems can be addressed during design. Good maintenance access is needed so crews can remove sediments from the forebay, alleviate clogging and make riser repairs.
5.9. ED Pond Material Specifications ED ponds generally use materials on site except for plantings, inflow and outflow devices such as piping and riser materials, possibly stone for inlet and outlet stabilization, and filter fabric for lining banks or berms. The basic material specifications for earthen embankments, principal spillways, vegetated emergency spillways and sediment forebays shall be as specified in Appendices A-D of the Introduction to the New Virginia Stormwater Design Specifications , as posted on the Virginia Stormwater BMP Clearinghouse web site, at the following URL: http://www.vwrrc.vt.edu/swc/NonProprietaryBMPs.html When reinforced concrete pipe is used for the principal spillway to increase its longevity, ‘O” ring gaskets (ASTM C-361) should be used to create watertight joints, and they should be inspected during installation. SECTION 6: REGIONAL AND SPECIAL CASE DESIGN ADAPTATIONS 6.1. Karst Terrain Active karst regions are found in much of the Ridge and Valley province of the Bay watershed, and complicate both land development in general and stormwater design in particular. Designers should always conduct geotechnical investigations in karst terrain to assess this risk in the planning stage. Because of the risk of sinkhole formation and groundwater contamination in regions with active karst, ED ponds are highly restricted. If these studies indicate that less than three feet of vertical separation exist between the bottom of the ED pond and the underlying active karst layer, ED ponds should not be used. If ED ponds are used, they must have an acceptable liner per Stormwater Design Specification No. 13 (Constructed Wetlands). 6.2. Coastal Plain The lack of sufficient hydraulic head and the presence of a high water table of many coastal plain sites significantly constrain the application of ED ponds. Excavating ponds below the water table creates what are known as dugout ponds where the water quality volume is displaced by groundwater, reducing pond efficiency and mixing and creating nuisance conditions. In general, shallow constructed wetlands are a superior alternative to ED ponds for the coastal plain environment. 6.3. Steep Terrain ED ponds are highly constrained at development sites with steep terrain. 6.4. Winter Performance Winter conditions can cause freezing problems within inlets, flow splitters, and ED outlet pipes due to ice formation. The following design adjustments are recommended for ED ponds installed in higher elevations of the Virginia:
SECTION 7: ED POND CONSTRUCTION SEQUENCE AND INSPECTION 7.1. Construction Sequence The following is a typical construction sequence to properly install a dry ED pond. The steps may be modified to reflect different dry ED pond designs, site conditions, and the size, complexity and configuration of the proposed facility. Step 1: Use of ED pond as an E&S Control. An ED pond may serve as a sediment basin during project construction. If this is done, the volume should be based on the more stringent sizing rule (erosion and sediment control or water quality). Installation of the permanent riser should be initiated during the construction phase, and design elevations should be set with final cleanout and conversion in mind. The bottom elevation of the ED pond should be lower than the bottom elevation of the temporary sediment basin. Appropriate procedures should be implemented to prevent discharge of turbid waters when the basin is being converted into an ED pond. Step 2: Stabilize Drainage Area. ED ponds should only be constructed after the contributing drainage area to the pond is completely stabilized. If the proposed pond site will be used as a sediment trap or basin during the construction phase, the construction notes should clearly indicate that the facility will be dewatered dredged and re-graded to design dimensions after construction is complete. Step 3: Assemble Construction Materials on-site, make sure they meet design specifications and prepare any staging areas. Step 4: Clear and Strip the project area to desired sub-grade. Step: 5 Install Project E&S Controls, including temporary dewatering devices, erosion and sediment controls, and stormwater diversion practices prior to construction. All areas surrounding the pond that are graded or denuded during construction are to be planted with turf grass, native planting, or other approved methods of soil stabilization. Step 6: Excavate the Core Trench and Install the Spillway Pipe. Step 7: Install the Riser or Outflow Structure and ensure the top invert of the overflow weir is constructed level at the design elevation. Step 8: Construct the Embankment and any Internal Berms in 8 to 12-inch lifts and compacted with appropriate equipment. Step 9: Excavate/Grade until the appropriate elevation for the bottom of the ED pond is reached and desired contours and acceptable side slopes are achieved. Step 10: Construct Emergency Spillway in cut or structurally stabilized soils. Step 11: Install Outlet Pipes, including downstream rip-rap apron protection. Step 12: Stabilize Exposed Soils with temporary seed mixtures appropriate for the pond buffer. All areas above the normal pool should be permanently stabilized by hydroseeding or seeding over straw. Step 13: Plant the Pond Buffer Area, following the pondscaping plan (see Section 7.5). 7.2. Construction Inspection Multiple construction inspections are critical to ensure that stormwater ponds are properly constructed. Inspections are recommended during the following stages of construction:
A construction inspection form for ED ponds can be accessed at the CWP website at www.cwp.org/postconstruction (see Tool #6 of Managing Stormwater in Your Community: A Guide for Building Effective Post-Construction Programs). For larger ED ponds, the expanded construction inspection form provided in Appendix B of CWP (2004) should be used. SECTION 8: ED POND MAINTENANCE 8.1. Maintenance Agreements Section 4VAC 50-60-124 of the regulations specifies a maintenance agreement to be executed between the owner and the local program. The section requires a schedule of inspections, compliance procedures if maintenance is neglected, notification of the local program upon transfer of ownership, and right-of-entry for local program personnel. Access to ED ponds should be covered by a drainage easement to allow inspection and maintenance. It is also recommended that the maintenance agreement include a list of qualified contractors that can perform inspection or maintenance services, as well as contact information for owners to get local or state assistance to solve common nuisance problems, such as mosquito control, geese, invasive plants, vegetative management and beaver removal. CWP (2004) provides some excellent templates on how to respond to these problems. 8.2. Maintenance Inspections Maintenance of ED ponds is driven by annual inspections that evaluate the condition and performance of the facility (see Table 3). Based on inspection results, specific maintenance tasks will be triggered. An annual maintenance inspection form for ED ponds can be accessed at CWP website at www.cwp.org/postconstruction (see Tool #6 of Managing Stormwater in Your Community: A Guide for Building Effective Post-Construction Programs). A more detailed maintenance inspection form is also available from Appendix B of CWP (2004). 8.3. Common Maintenance Issues ED ponds are prone to a high clogging risk at the ED low flow orifice. These aspects of pond plumbing should be inspected at least twice a year after initial construction. The constantly changing water levels in ED ponds make it difficult to mow or manage vegetative growth. The bottom of ED ponds often become soggy, and water-loving trees such as willows may take over. The maintenance plan should clearly outline how vegetation in the pond and its buffer will be managed or harvested in the future. Periodic mowing of the stormwater buffer is only required along maintenance rights-of-way and the embankment. The remaining buffer can be managed as a meadow (mowing every other year) or forest. The maintenance plan should schedule a shoreline cleanup at least once a year to remove trash and floatables that tend to accumulate in the forebay, micropool and on the bottom of ED ponds. Frequent sediment removal from the forebay is essential to maintain the function and performance of an ED pond. Maintenance plans should schedule cleanouts every 5-7 years, or when inspections indicate that 50% of forebay capacity has been lost. Designers should also check to see whether removed sediments can be spoiled on-site or must be hauled away. Sediments excavated from ED ponds are not usually considered toxic or hazardous, and can be safely disposed by either land application or land filling.
SECTION 9: COMMUNITY AND ENVIRONMENTAL CONCERNS There are several community and environmental concerns about ED ponds that can be anticipated during design, as follows:
SECTION 10: DESIGN REFERENCES Cappiella, K., T. Schueler and T. Wright. 2006. Urban Watershed Forestry Manual: Part 2: Conserving and Planting Trees at Development Sites. USDA Forest Service. Center for Watershed Protection. Ellicott City, MD Cappiella, K. et al . 2007. Urban Watershed Forestry Manual: Part 3: Urban Tree Planting Guide. USDA Forest Service. Center for Watershed Protection. Ellicott City, MD Cappiella, K., L. Fraley-McNeal, M. Novotney and T. Schueler. 2008. The next generation of stormwater wetlands. Wetlands and Watersheds Article No. 5. Center for Watershed Protection. Ellicott City, MD Center for Watershed Protection. 2004. Pond and Wetland Maintenance Guidebook. Ellicott City, MD. Maryland Department of Environment (MDE). 2000. Maryland Stormwater Design Manual. Baltimore, MD Schueler, T., D. Hirschman, M. Novotney and J. Zielinski. 2007. Urban stormwater retrofit practices. Manual 3 in the Urban Subwatershed Restoration Manual Series. Center for Watershed Protection, Ellicott City, MD Virginia Department of Conservation and Recreation (VA DCR). 1999. Virginia Stormwater Management Handbook. Volumes 1 and 2. Division of Soil and Water Conservation. Richmond, VA Appendix 15-A This appendix provides a general discussion of the channel protection method for ED ponds. The Virginia Stormwater Management Handbook (Latest Edition) should be consulted for allowable computation methods for channel protection. Step 1: Compute the runoff volume produced from the post-development 1-year, 24 hour design storm event, using TR-55, and adjusted CNs to account for upland runoff reduction. Step 2: Use the Kerplunk method which assumes the pond volume (above the permanent pool or basin floor) instantaneously fills up. Determine the storage volume and Cpv maximum invert elevation using the short-cut method described below. Step 3: Set the Cpv orifice invert above the permanent pool elevation and size the initial orifice diameter to drain the entire Cpv volume in 24 hours. Step 4: Compute the average peak discharge rate for the Cpv event (i.e., Cpv/24). Step 5: Using TR-20 or other accepted storage indication routing tool,, route the runoff through the pond and check to make sure that the peak discharge for Cpv does not exceed twice the average discharge, and that it meets the minimum 12 hour detention time. Note: No permanent pool is involved in the design (although a micropool is recommended to keep orifice from clogging). In most cases, an extended detention pond is utilized after upland runoff reduction practices provide some storage for channel protection and flood control design storms (in some cases, the runff reduction practices can be incorporated within the extended detention pond if adequate pretreatment is provided (e.g., sand filter or bioretention in the pond floor). Shortcut Sizing for Channel Protection: Storage Volume Estimation This section presents a modified version of the TR-55 (NRCS, 1986) short cut sizing approach. The method was modified by Harrington (1987) for applications where the peak discharge is very small compared with the uncontrolled discharge. This often occurs in sizing detention for the 1-year, 24-hour storm event. Using TR-55 guidance, the unit peak discharge (qu) can be determined based on the Curve Number and Time of Concentration (Figure 15-A.1). Knowing qu and T (extended detention time), qO/qi (peak outflow discharge / peak inflow discharge) can be estimated using Figure 15-A.2. Then using qO/qi, Figure 15-A.3 can be used to estimate VS/Vr. For a Type II or Type III rainfall distribution, VS/Vr can also be calculated using the following equation: VS/Vr = 0.682 – 1.43 (qO/qI) + 1.64 (qO/qI)2 – 0.804 (qO/qI)3 Where: VS = required storage volume (acre-feet) The required storage volume can then be calculated by: VS = (VS/Vr)(Qd)(A) Where: VS and Vr are defined above
Figure 15-A.1. Unit Peak Discharge for Type II Rainfall Distribution (Source: NRCS, 1986)
Figure 15-A.2. Detention Time vs. Discharge Ratios (Source: adopted from Harrington, 1987)
Figure 15-A.3. Approximate Detention Basin Routing For Rainfall Types I, IA, II, and III (Source: NRCS, 1986) |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||